US Hwy 160 Hawkins St. Signal and Curb Ramps Cortez
Project Type
Aggregates
Construction
Location
Cortez
Owner: CDOT Colorado Department of Transportation
General Contractor: Oldcastle SW Group, Inc./Four Corners Materials
Subcontractors or Key Contractors: Goff Engineering & Surveying, Western Gravel Construction, Horizon Environmental Services, Alert Traffic Control, and TY Striping
Materials Used on Project and Quantities:
- Base Course Gravel – 500 tons
- Concrete Pavement (Fast Track) – 100 CY
- ADA Compliant Concrete Sidewalk/Curb & Gutter – 200 CY
- Electrical Conduit – 2,000 LF
- Signal Poles (40 Ft. avg.) – 4
Four Corners Materials crews removed the existing sidewalk, curb, and gutter and replaced them with new ADA compliant sidewalks, ramps, and curbs. Additionally, crews installed a new traffic signal at the intersection of US Hwy 160 and Hawkins Street at the east end of Cortez, CO.
"Great job - Project crew had a learning curve at the beginning and was able to complete the project safely, on time, and within budget."